Status of Projects Encountering Problems

Showing 21-33 of 33 items.
#Project NameFindingPossible Reason/ CauseRecommendation
21Sangley Airport Development ProjectDuring the course of implementation, the DOTr finds it necessary to improve and ensure the flooding situation along the runway strip be permanently mitigated.
The existing airport runway lies along an airstrip closer to the sea with an elevation of only +2.00M from the sea level.
The DOTr using the CY 2020 Budget for Sangley, intend to improve further the drainage system by way of providing additional pumps along air strip, extending the sheet piling works and the addition of open line channels to ensure unexpected flooding in the future is mitigated.
22Sangley Airport Development ProjectThe DOTr finds it necessary to improve the services to the public by providing another terminal to cater future passenger/cargo increase. The airport has an available area that can still accommodate a terminal building or hangarage with an area of 3,560 sqm.
The original design of Sangley Airport dictates that the facilities to be provided will be used for General Aviation operation. With the current government trust to have the airport open for commercial operation, there is a need to expand the area of the PTB or Hangarage that can accomodate aircrafts for Cargo within the available area.
The DOTr with the concurrence of CAAP intend to provide additional Hangarage within the available area instead of expanding the PTB.
23Light Rail Transit (LRT) 1 Cavite ExtensionDelay in the relocation of utilitiesDelay in the approval of MOA between LRTA and utility providers

Delay in the review and approval of MOA by utility companies (external).

Delay in the concurrence of the relocation plan by LRMC (external).
Continuously monitor the approval of MOA, attend coordination meetings with the stakeholders and provide pertinent documents as required

Continuously follow-up on MOA from utility companies, attend coordination meetings with the stakeholders and provide pertinent documents as required.

Continuously follow-up on the concurrence of the relocation plan by LRMC.
24Light Rail Transit (LRT) 1 Cavite ExtensionDelay in the delivery of LRVs and depot works as per scheduleDue to imposed community quarantine and/or COVID-19 pandemic, LRV manufacturing were closed and on-site works were suspendedAdopt Work-from-Home (WFH) and skeletal work schedule. Project Contractors and Consultants continue working on the designs, drawings, test protocols and other documentations.
25Isolation and Characterization of Photofermenting Microorganism for Biohydrogen ProductionProcurement delaysAdministrative impedimentsHasten the process of procurement
26Isolation and Characterization of Photofermenting Microorganism for Biohydrogen ProductionFor the period being reported collection of some data were affected however, promising photofermenting microorganism for biohydrogen production were isolated
and characterized
Lockdown due to COVID-19 pandemicWill resume data collection once lockdown is eased
27Health Sufficiency (LIKAS): Philippine Actinomycete as Source of BiosurfactantLate submission of audited financial and terminal technical reportOther purchase orders and disbursement vouchers still in process
which was greatly hampered by the lockdown due to COVID 19
Hasten the processing of documents
28Bat Guano from a Philippine Cave as Potential and Sustainable Source of Antibiotic-Producing StreptoDelayed conduct of research project methodologiesOcular visit to the collaborating/partner institution was not made due to the enhanced community quarantine.

Processing of documents (i.e. PPMP, MOU) were placed on hold due
to the ongoing enhanced community quarantine.
Documents should be facilitated and fast tracked once the enhanced community quarantine is lifted.
29Health Sufficiency - LIKAS (Likas Yaman sa Kalusugan)Delayed submission of financial and technical reportsProcessing of documents were affected/put on hold due to the enhanced community quarantineHasten and facilitate the liquidation and auditing processes after the enhanced community quarantine is lifted
30Health Sufficiency - LIKAS (Likas Yaman sa Kalusugan)The researchers were unable to yield good molecular
analysis results.
Have more attempts using different/new set of primers.
31Health Sufficiency - LIKAS (Likas Yaman sa Kalusugan)Delayed submission of financial and technical reportsProcessing of documents were affected/put on hold due to the enhanced community quarantineHasten and facilitate the liquidation and auditing processes once the enhanced community quarantine is lifted.
32Development and Use of Nanobiopesticide for the Control of Fusarium Wilt on High Value CropsThe field set-ups in Tuba, Benguet were rescheduled in December 2019
Inclement weather conditions in the region
The project's request for three-month extension without additional funding was approved in order for the project to catch-up the delayed activities.

33Development and Use of Nanobiopesticide for the Control of Fusarium Wilt on High Value CropsDelayed screenhouse testing of nanobiopesticide against Fusarium oxysporum f. sp. cubense Tropical Race 1 (Foc TR1)
Tissue-cultured Latundan plantlets are needed for screenhouse testing of nanobiopesticide against Fusarium oxysporum f. sp. cubense Tropical Race 1 (Foc TR1). However, the National Plant Genetic Resources Laboratory (NPGRL) of IPB is having a hard time propagating the needed plantlets due to contamination. There is no available Latundan plantlets in other plant tissue culture laboratories and nurseries.
The project's request for three-month extension without additional funding was approved in order for the project to catch-up the delayed activities.